Texas Lower Colorado River AuthorityLCRA Transmission Services Corporation and Oncor were responsible for identifying potential routes to the Public Utility Commission of Texas. Throughout the process, LCRA TSC and Oncor representatives received extensive feedback from hundreds of stakeholders through both formal and informal conversations.
Over time, LCRA TSC and Oncor modified some preliminary segments for reasons discussed during testimony and documented in PUC files. This is part of the normal process for transmission line routing before the PUC.
LCRA TSC and Oncor have worked diligently throughout this process to be transparent, provide workable options for landowners and meet the directives of the PUC.
LCRA TSC and Oncor submitted the application for the Big Hill to Sand Lake 765-kV project application on Jan.16, 2026, and submitted the Big Hill County East to Bill Hill 765-kV project on March 26, 2026.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.